Motors & Loads calculator
Motor Control Panel Load Calculator
This page is an MCC feeder-ampacity screen. For a 480 V lineup with one 65 A largest motor, 96.6 A of remaining motors, and 3 kVA of continuous non-motor load, the required feeder ampacity screens at 182.36 A before spare capacity and 227.95 A with a 25% planning adder.
Updated July 10, 2026
A 480V MCC with one 65A largest motor, 96.6A of remaining motor FLC, and 3 kVA of continuous non-motor load screens at about 182.4A of required feeder ampacity before any planning spare capacity is added.
Feeder ampacity = 1.25 x largest motor FLC + remaining motor FLC + 1.25 x continuous non-motor current + non-continuous non-motor current.
Enter the largest motor FLC, combined remaining motor FLC, and non-motor kVA below to screen MCC feeder ampacity and a planning spare-capacity view.
Example Calculations
How to Use
What this motor control panel load calculator does
This page is for one specific question: what feeder ampacity should you screen when a motor control panel or motor control center serves multiple motors plus optional line-side non-motor load? It is not a full MCC design package, breaker selector, conductor selector, or SCCR review tool.
Feeder-load basis
The screen follows the familiar multiple-motor feeder logic used in U.S. practice: one largest motor is counted at 125%, the remaining motors are counted at 100%, continuous non-motor load is counted at 125%, and non-continuous non-motor load is counted at 100%.
Required feeder ampacity = 1.25 x largest motor FLC + remaining motor FLC + 1.25 x continuous non-motor current + non-continuous non-motor current
Inputs that matter
- Largest motor full-load current: use one motor only, even if several motors tie for largest FLC
- Combined remaining motor FLC: add every other motor on the same feeder at 100%
- Continuous non-motor load: convert the stated kVA to current at the selected panel voltage, then apply 125%
- Non-continuous non-motor load: convert the stated kVA to current at the selected panel voltage and count it at 100%
Worked screening example
Suppose a 480 V MCC serves one 65 A largest motor, 96.6 A of remaining motors, and 3 kVA of continuous non-motor load.
- Largest motor contribution: 65 A x 1.25 = 81.25 A
- Remaining motors contribution: 96.6 A
- Continuous non-motor contribution: 3 kVA x 1000 / (sqrt3 x 480) x 1.25 = 4.51 A
- Required feeder ampacity: 81.25 + 96.6 + 4.51 = 182.36 A
If you add a 25% planning spare-capacity allowance, the planning screen rises to about 227.95 A. That planning result is useful for budgeting or bucket-space discussions, but it is not a substitute for the actual design basis and final equipment schedule.
Scope limits
- This page assumes you already know the motor full-load current values you want to use.
- This page does not derive motor FLC from horsepower or nameplate efficiency assumptions.
- This page does not size breakers, conductors, overloads, branch-circuit protection, or SCCR.
- This page does not prove that multiple motors will or will not run together. If diversity is part of the design basis, document it outside this screen.
Use the Motor Current Calculator when you still need a preliminary current basis. Use the Motor Cable Size Calculator when the next question is branch-circuit conductor screening. Use the Short Circuit Calculator when the real concern is fault current and downstream duty instead of feeder ampacity.
Common Applications
More applications. Open to review 2 additional use cases.
Frequently Asked Questions
Should I enter horsepower or actual motor full-load current on this page?
What if two or more motors tie for the largest full-load current?
Can I use this page to pick the MCC main breaker or feeder conductor?
Why does the page ask for non-motor load in kVA?
Related Calculators
Estimate formula running current from HP or kW, voltage, efficiency, and power factor, then compare against NEC table FLC when needed.
Screen NEC table motor conductor size with ampacity derating, termination limits, and branch-circuit voltage drop.
Evaluate panel loading, demand, and spare capacity against NEC-style design assumptions.
NEC-oriented standard breaker review-point screen with simplified conductor protection checks.
Screen available fault current from transformer impedance, feeder impedance, or known source impedance.
Estimate demand load and service ampacity using NEC-style demand and diversity factors.